Timeline

Project Timeline  
2008-2010 ➨ Pre-planning stage
➨ Feasibility studies
➨ Environmental impact studies
➨ Community engagement
➨ Preparation of planning application
August 2010 ➨ Planning application submitted
March 2012 

Winter – Spring 2015

➨ Planning permission granted 

➨ Minor enabling works

➨ Community engagement

Summer 2015 ➨ Construction begins and continues
for 20 months
➨ Community engagement
Autumn/Winter 2015 ➨ First call for applications for the Sliabh Bawn Community Fund
June 2016 ➨ Sliabh Bawn recreation Phase 1 works completed
July-Oct 2016 ➨Wind turbine deliveries
July-Dec 2016 ➨ Wind turbine installation
Spring 2017 ➨ The Sliabh Bawn Wind Farm is operational
Summer 2017 ➨ Sliabh Bawn recreation Phase 2 works scheduled for completion and Coillte’s ‘open forest’ policy resumes
Spring 2018 ➨ New local evaluation panel for community Benefit Fund established.
Spring 2019 ➨ New plantation established at Sliabh Bawn comprising 11 Irish native tree species.